Two major roadworks schemes begin this week to improve the
roads in Aylesbury. For the next two weeks works will take place under road
closures at night, to minimise traffic disruption, on the A41 Aston Clinton
Road and the A413 Buckingham Road. While the dual works will mean there will be
two diversions in place at the same time causing some delays for drivers, the diversions
do not overlap at all and have been scheduled to start after 7pm to avoid peak
travelling hours.
The A41 Aston Clinton Road works are taking place on a small
stretch outside the Holiday Inn, as work finishes on the new junction there.
The road will be shut from 7.30pm to 6am, Monday to Friday only, until 4th
August with an additional overnight closure planned for 7th August. The work
will include highway improvement, a signalised junction, new traffic islands,
the planning and re-surfacing of a 500 metre stretch of the A41, and 170 metres
from the junction with New Road going south. There will also be some white
lining and loop cutting for the signalised junction. There will be signed
diversion routes in place, with HGVs from the Tring direction diverted through
Wendover, and cars through Weston Turville.
The A413 Buckingham Road carriageway resurfacing will
commence tomorrow night, 25th July, on an area stretching from the
traffic lights by the Horse and Jockey pub up to just beyond Prince Rupert Drive.
The works should take ten nights to complete, not including any weekend
working, but are weather dependant. Access to Watermead and Oliffe Way will be maintained however
will be subject to short delays at times to ensure the safety of the public and
crews on site. Footway access will be maintained at all times. The diversion
route is via A4157 Weedon Road, A41 Bicester Road, and Martin Dalby Way. These works
have been delayed by a day due to the overrunning Winslow High Street works
which were disrupted by last week’s heavy rain.
County councillor Mark Shaw, cabinet member for
transportation, welcomes the road improvements, saying:
“These works are much needed for Aylesbury’s busy road network – some disruption is inevitable but the work has been scheduled to get all that disruption over and done with in a period of just two weeks, rather than run the two schemes back to back and face at least four weeks of diversions. We thank residents and drivers for their patience and forbearance with the noise and minor delays, and hope that once the work is done and the roads are looking fabulous that it will have been worth it!”
For more information on roadworks in Aylesbury and
surrounding areas, visit the Transport for Buckinghamshire website: buckscc.gov.uk/services/transport-and-roads/